Re-roof and tear-off.

Removal of the existing assembly, deck repair, wood nailers and blocking, then a new system to the spec.

The work

From the old roof down to the deck, and back up.

A re-roof replaces the whole assembly. The existing membrane, insulation and cover board come off in sections sized to what can be closed in the same day. The deck is inspected and damaged areas are replaced. Wood nailers and blocking at edges and curbs are replaced or added to the height the new insulation needs. Then the new system goes down layer by layer, from the vapor retarder the spec may call for up to the edge metal.

On an occupied building, the sequence keeps the interior dry. Each day's tear-off is covered before the crew leaves, and weather decides how much is opened.

How we work

Every roof starts as a bid.

  1. 01

    From your drawings

    Roof plans, details, mechanical sheets and the Division 07 spec.

  2. 02

    Measured to scale

    Quantities checked against a known dimension before they count.

  3. 03

    Priced line by line

    Each line from our own unit-cost database, alternates on their own.

  4. 04

    Signed off

    An estimator approves every proposal before it goes out.

In the field

From tear-off to a new roof

  1. 01
    Aerial view of a white commercial roof with tapered crickets between drains
    Tapered insulation and drains
  2. 02
    White TPO membrane turned up a parapet and capped with bronze metal coping
    New membrane up the parapet
  3. 03
    Hot-air welding machine on a white TPO seam on a commercial roof
    Seams welded and checked

Recover or replace

When the old roof has to come off.

A recover may be allowed over one existing roof when the adopted code and the manufacturer allow it and the existing roof is dry and sound. Where two or more roofs exist, or the insulation is wet, the code requires a tear-off. A recover also adds weight. A moisture survey and a look at the deck settle the question before the scope is final.

A tear-off has another benefit: when a roof is removed to the deck, the energy code the city has adopted can require insulation to current R-values. The spec and the permit set the target, and we price to it.

Aerial view of a commercial re-roof: old gravel roof, bare deck and new white membrane

How we price it

Demolition and new work on separate lines.

  • Tear-off by area and by layer, with haul-off and disposal
  • Deck repair as an allowance or unit price per square foot, so it can be adjusted to what is found
  • Wood nailers and blocking by linear foot
  • The new system by layer: insulation, cover board, membrane, flashing, edge metal
  • Tie-ins to roof sections that stay in place

Unit prices for hidden conditions are named in the proposal, so a change order is a quantity times a price you already agreed to.

Gypsum cover board and insulation plates staged on a commercial roof deck
New insulation and cover board go down the day the old roof comes off.

FAQ

Questions we get.

How long does a commercial re-roof take?

It depends on area, the number of layers coming off, rooftop equipment and weather. The proposal includes a duration once we have the drawings and the site conditions.

Can the building stay open during a re-roof?

Usually. Work is sequenced by area, openings are closed in each day, and noisy work can be scheduled around the occupants. Odor from adhesives or hot work is planned for with the owner.

What happens if the deck is worse than expected?

We stop, photograph it and tell the GC or owner the same day. Repair is priced from the unit price in the proposal.